WP2047

Project Area: S 42nd St from Mayberry St to Pacific St

Start: TBD

End: TBD

WP2047

Project Update (9/18/2023): The 42nd Street road closure is necessary for both gas and water main work to be performed by Backlund Plumbing, Q3 Contracting and M.U.D. The road closure starts September 18, 2023 and will continue for approximately five weeks, barring any unplanned delays. Customers who live in the road closure area will continue to have access to their properties using an exit/entrance on the south end of the road closure at 42nd and Pacific. For the safety of everyone, please use caution when traveling in this area. There will be a lot of work being performed.