Project Area: Howard Ln, Molley St and Stark St between S 2nd St and N 4th St
Start: 06/26/2023
End: TBD
Public Notice and Contact Info:
Description:
M.U.D. will perform a future water main infrastructure replacement project. Customers will see technicians in the project area investigating the water services of each of the homes. Project start date is to be determined.
Project Update (6/19/23): M.U.D. anticipates moving equipment and supplies into the project area the week of June 26, barring any unplanned delays. We will start more invasive work after the July 4th holiday. This project has the potential to stop for the winter months and then be completed in Spring 2024 due to freezing weather. We appreciate your patience as we work to invest in your neighborhood.
Project Update (7/17/23): Crew currently installing water main north of Howard Ln on N Molley St and will work south
Project Update (9/20/2023): Water main work is anticipated to be completed at the end of October 2023, barring any unplanned details. Please keep in mind the site restoration may not be complete prior to Halloween and use caution when walking in project areas. For more details, click on WP1959 above.