R2000

Project Area: 168th Ave from Pine St to Shirley St

Start: TBD

End: TBD

Public Notification & Contact Info.

R2000

 

Project Update (7/17/23): M.U.D. planned to start this project in June, however this has been changed due to delays occurring on other current projects. We anticipate starting construction when the other projects are completed and that is now looking to be approximately late July or early August.

Project Update (9/27/2023): Water main work started August 14 and will continue for approximately three months, barring any unplanned details. Please keep in mind site restoration may not be completed prior to Halloween – use caution when walking in project areas. For more details, click on R2000 above.

Project Update (10/16/2023): To perform utility work, M.U.D. needs to close Shirley Street from 168th Street to 169th Circle for approximately three weeks. We anticipate this project to be completed in less than one month. For more details, click on R2000 above.