WP1936

Project Area: Walnut Street to Martha Street and S 48th Street to S 50th Street

Start: August 2025

End: TBD

WP1936

 

Update 11/19/2025. Our contractor, Backlund Plumbing, will soon be excavating on both sides of 50th Street to reconnect each individual water service to the new main. Because southbound traffic is currently closed, northbound traffic must also be closed to safely complete this work. Please note, the closure will only be during daytime hours.

 

ROAD CLOSED TO THRU TRAFFIC

50th Street from Center Street to Frances Street

Start. Monday, December 1, 2025

Time. 9:00 a.m. – 3:00 p.m. Monday – Friday; the closure will reopen to traffic each morning and afternoon to accommodate the rush hours

Duration. Two weeks, barring any unplanned delays

Other Impacts. The crew will coordinate with trash and U.S. Postal Service providers to ensure their services can continue without disruption. Driveways will remain accessible. If the crew is ever blocking your access, please kindly ask them to move temporarily—they’d be happy to accommodate.

Crews are continuing their work south of Center Street and are progressing from west to east. We appreciate your patience as we continue working on this project.