Project Area: Harrison St to Park View Blvd and Pine Dr to S 86th St
Start: Anticipated June 2025
End: TBD
Update 11.26.2025
Below is an overview of the remaining work scheduled for the rest of December.
Sidewalk pour-back is planned on the following streets:
- Glenview Dr.
- Driveway of the Alpine Village Apartment Complex
- Wilbur St.
- Monterrey Dr.
- Pine Dr.
In addition, all soft surface restoration is expected to be completed during the month of December.
Weather permitting, the project is anticipated to be fully completed by the end of the year.
We appreciate your patience as crews complete the final steps of this project. If you have any questions, please feel free to reach out.