Project Area: Fairview St to Virginia Ave and Fort Crook Rd to N 3rd St
Start: May 2024
End: TBD
Update 6/06/2025
Main Installation. Completed.
Water Service Reconnections. Approximately 30 services remain to be reconnected (duration approximately 4-6 weeks) on the south end of the project area. Backlund Plumbing performing the work.
Abandonment. The final step will be to abandon the old main and take it out of service. This will be scheduled after all water service work is completed.
Thank you for your patience as we work to complete this project in your neighborhood.