WP1960

Project Area: S 46th Ave from Frances St to Bancroft St and S 48th Ave from Martha St to Spring St

Start: December 2025

End: TBD

Click here for more information: WP1960

 

Update 7/24/2026

New Water Main Installation. Completed

Individual Water Services Reconnected to the New Main. 138 / 156 completed. This project is anticipated to be completed within one month.

Sidewalk and Street Restoration. Ongoing. Areas that can be restored at this time will be completed. Locations where water service work is still in progress will be restored after the plumber has reconnected the water service.

Lawn Restoration. Ongoing. Areas that can be restored at this time will be completed. Locations where water service work is still in progress will be restored after the plumber has reconnected the water service.

Sprinkler Systems. Any systems damaged during the project have been repaired. If you notice any issues or damage, please report them so they can be addressed. Send an email to Customer_Engagement@mudnebr.com or call 402.504.7770.

We would like to sincerely thank you for your patience and understanding during our water main replacement project in your neighborhood. We recognize that construction work can bring temporary inconveniences, and we truly appreciate your cooperation while our crews worked to complete this important water system upgrade. This improvement will help enhance reliability and service for your area for years to come.