Project Area: Walnut Street to Martha Street and S 48th Street to S 50th Street
Start: August 2025
End: TBD
Update 11/19/2025. Our contractor, Backlund Plumbing, will soon be excavating on both sides of 50th Street to reconnect each individual water service to the new main. Because southbound traffic is currently closed, northbound traffic must also be closed to safely complete this work. Please note, the closure will only be during daytime hours.
ROAD CLOSED TO THRU TRAFFIC
50th Street from Center Street to Frances Street
Start. Monday, December 1, 2025
Time. 9:00 a.m. – 3:00 p.m. Monday – Friday; the closure will reopen to traffic each morning and afternoon to accommodate the rush hours
Duration. Two weeks, barring any unplanned delays
Other Impacts. The crew will coordinate with trash and U.S. Postal Service providers to ensure their services can continue without disruption. Driveways will remain accessible. If the crew is ever blocking your access, please kindly ask them to move temporarily—they’d be happy to accommodate.
Crews are continuing their work south of Center Street and are progressing from west to east. We appreciate your patience as we continue working on this project.