WP1736

Location: Ponca Rd – Calhoun Rd to N 40th St and N 42nd St from Ponca Rd to the north
Start Date: 03-14-22
End date: 05-31-23
Public Notice & Contact Info.
Update 3/01/2023:

M.U.D.’s contractor, Heimes Corp., has completed installation of the water main in the project area. Old hydrants and valves are currently being removed. Restoration of the project area is scheduled for this spring (seed and matting, any settlement issues, etc.). We appreciate your patience as we work to complete this project.

Update 1/23/2023:

Water main installation: 99% complete

Water services reconnection work: 80% complete

Water main abandonment: 0% complete

Restoration: to be performed in Spring 2023 due to current cold weather

Project status: Heimes is currently working on water service reconnections and abandonment.

Update, April 7, 2022:

As work progresses, the temporary traffic lights installed in Ponca Road will soon be moved approx. 1,000 feet to the north.

Update, March 18, 2022:

A technician(s) is currently looking for underground utilities in the project area – you may see test hole(s) which are used to expose any underground utilities. Two temporary stop lights have been installed in Ponca Road. Digging will start next week on the south end of the project near Calhoun Road.