WP1735

Location: Florence Heights Blvd area
Start Date: 06-01-21
End date: 12-01-21
Public Notice & Contact Info.
Description

UPDATE 10/01/2021 Our contractor, Heimes Corp., has finished installing the new water mains in the project area. Now, they must make connections from each home/business to the new mains (this work has already started on the south end of the project and will progress north). This work entails digging a small hole in the front of each home/business (in the right-of-way) to make the connection to the new main. After all connections are complete, the old water main will be abandoned and restoration of the project area will occur. This project is anticipated to take approximately 2 more months, barring any unplanned delays.