WP1719

Location: Leavenworth St to Dodge St and S 69th St to S 71st St
Start Date: 06-13-22
End date: TBD
Public Notice & Contact Info.
Description

Project Update (11/09/2022): Water main installation continues on this project and is anticipated to be completed around March 2023, barring any unplanned delays. After the mains are installed, all homes and businesses in the project area will be reconnected to the new mains. This reconnection work will require an excavation near each water stop box and result in a brief water service interruption. You will be notified prior to any planned water service interruption.

Project Update (7/17/2023): Water main installation completed; currently working on reconnection work from homes to new main; abandonment of old main and restoration remains.

Project Update (8/11/2023): All water mains have been installed and services have been reconnected to the new mains. Repaving of streets and sidewalks should be completed very soon. Restoration of lawns and landscaping should be completed by end of August or September. All work is barring any unplanned delays.

Project Update (9/1/2023): All water main has been installed, services have been reconnected, and restoration has been completed.