R2035

Location: S 156th St from Pacific St to Nottingham Dr
Start Date: 02-07-22
End date: TBD
Public Notice & Contact Info.
R2035 letter.pdf (806.34 KB)
Description

Update 1/25/2023 – The gas portion of this project was completed in 2022. The water portion of this project is anticipated to start next week, January 30 and continue for a few weeks in 156th from Pacific to south of Leavenworth. Work in 156th will be performed within the current lane restriction. An additional lane restriction may occur in Pacific at 156th. For the safety of you and our crews, please slow down when driving in the area. We appreciate your patience as we work to complete this project ahead of the City of Omaha’s road improvement project.