7-21-2021 UPDATE The water portion of this project is nearly complete. Gas work will begin next week on the east side of S 168th St in the following areas: north of Ehlers St to Rolling Ridge Rd and near H Circle. This gas work is expected to take 2-3 weeks, barring any unplanned delays.
6-02-2021 UPDATE crews continue to work in the areas of 168th St and Patterson Dr and 168th St and Ehlers St; traffic will soon be impacted with lane restrictions near Ehlers St–for the safety of our crews, please slow down when driving in the area; gas work will begin soon in 168th St north of Orchard Ave; all work will continue barring any unplanned delays.
3-15-2021 UPDATE crews will be moving to the area in 168th Street between Patterson Drive and Rolling Ridge Road this week; duration is estimated at 2 months, barring any unplanned delays
1-14-2021 UPDATE crews will be moving to the H Circle area sometime next week; duration is estimated at 2 months, barring any unplanned delays